One of the most common causes of procurement failure is unrealistic timeline expectations. Factory capacity, material lead times, and shipping logistics all compound. Here are realistic windows by order size.
Order Volume Tiers
- 500–2,000 units: 6–8 weeks production + 2–3 weeks sea freight
- 2,000–10,000 units: 10–14 weeks production + 3–4 weeks sea freight
- 10,000+ units: 16–20 weeks production + 4–5 weeks sea freight
Buffer Recommendations
Always add a 2-week buffer for customs clearance and in-country logistics. For air-sensitive procurement (uniforms needed for a specific operational date), factor in air freight costs as a contingency.
Material Lead Times
Ripstop fabric, ballistic nylon, and specialty zippers often have 4–6 week independent lead times. Confirm material availability before finalising your production schedule.